Fast, Cost-Effective Fire Station Expansion in Groveland, Florida

4 mins read

Fast, Cost-Effective Fire Station Expansion in Groveland, Florida
Client Industry
Government
Project Type
Fire Station
Size
1,200 sq. ft.
Location
Groveland, Florida
Usage
Living Quarters
  • 1,200 sq. ft. refurbished modular building
  • Less than three months from project start to completion
  • Fully equipped living quarters with bedrooms, an eat-in kitchen, laundry facilities, storage, and two restrooms

The Project

The Groveland Fire Department provides fire, rescue, and emergency medical services to approximately 20,000 residents in Groveland, Florida. With three strategically located fire stations responding to more than 2,300 calls annually, the department must carefully position its facilities to support timely emergency response across the community.

In 2020, The Groveland Fire Department decided to open a new service location, and they knew modular space construction was the right fit. 

The Challenge

What They Needed

  • A new fire station to support the department’s emergency response services
  •  Comfortable living quarters where firefighters could rest between calls
  •  A cost-effective alternative to traditional construction
  • A fast project timeline to get the new station operational
What BOXX Modular Delivered
  • A refurbished 1,200 sq. ft. modular building converted for fire station use
  • Delivery one month after contract signing, with the facility ready for occupancy approximately two months later
  • Multiple bedrooms, an eat-in kitchen, a laundry facility, storage room, and two restrooms

The Outcome

 In order to reduce costs and improve speed of operations, the Groveland Fire Department chose to convert a used modular building into their finished project.

The refurbished building was able to provide 1,200 square feet of comfort to the fire and rescue staff. Groveland’s firefighters now have a relaxing environment and everything they may need, as they await their community’s emergency calls. The renovated building comes equipped with an eat-in kitchen, multiple bedrooms, a storage room, laundry facility, and two restrooms. The entire construction project took less than three months to complete. Their building was delivered a month after contract, and ready for occupancy just 2 months later. On November 2nd, 2020, new Fire Station #3 officially opened.  